UPS Northeast Regional HUB

Project Info

Kinsley delivered an extensive site work package for a 775,000-sq-ft trucking center.

This four phase project included:

  •  Moving 800,000 cubic yards of dirt
  • Installing 12 miles of underground utilities including 275 concrete structures
  • Performing compaction grouting for the building foundations
  • Excavating and installing two 695,000 cubic foot capacity underground storm water storage facilities
  • Building nine individual retaining walls
  • Constructing and paving 7,700 linear feet of new access roadway

The underground storm water detention systems consisted of 1,044 individual precast concrete pieces, taking 373 tractor trailer loads to deliver.

Project:

Large Distribution Facility

Division:

Civil

Market:

Warehouse/Distribution

Location:

Middletown, PA

Client:

United Parcel Service

Architect:

Snyder, Secary and Associates, LLC

Size:

192 acres